Chapter 3
Installing the System
Performing a Visual Inspection and Completing the Installation
135
Performing a Visual Inspection and Completing the Installation
After booting the system, carefully inspect it and reinstall the EMI panels. Here are the steps required to
perform a final inspection and complete the installation:
Step 1. Visually inspect the system to verify that all components are in place and secure.
Step 2. Check that the cables are secured and routed properly.
Step 3. Check that the cell board ejectors are secure (Figure 3-54).
If the ejectors are broken or open, the cell board is disconnected.
Figure 3-54 Cell Board Ejectors